Construction


The following is a guide to the construction process of your SIP home one site:

  • Day 1
    Fit, align and level sole plate and PB plate.
    Fit, align and level sole plate and PB plate.

  • Day 2
    Erect ground floor walls, beams, and joisting.
    Erect ground floor walls, beams, and joisting.

  • Day 3
    Deck out first floor, align and fit PB plate, start erecting 1st floor walls.
    Deck out first floor, align and fit PB plate.start erecting 1st floor walls.

  • Day 4
    Balance of 1st floor walls, beams, joists, attic deck.
    Balance of 1st floor walls, beams, joists, attic deck.

  • Day 5
    Erect gables, ridge beams, purlins, trusses (where required), fit roof panels.
    Erect gables, ridge beams, purlins, trusses (where required), fit roof panels.

  • Day 6
    Fit roof panels, finish out details - e.g membrane details, checklist, sign-off.
    Fit roof panels, finish out details - e.g membrane details, checklist, sign-off.



Watch our demonstration DVD which highlights the benefits and features of SIP Energy Homes


SIP Energy Portable & Demountable Systems


    Visit our stand at the Ecobuild 2010 Exhibition in Earls Court, London on Tuesday 2nd - Thursday 4th March 2010.


Download our brochure here.